As part of the massive gas infrastructure project aimed at separating the industrial and the domestic sector, SSGC has completed two major projects in Karachi that would enable better gas pressures :
In December 2023, a 16” dia. x 6.2 Km pipeline from Pakistan Steel Mills to Yousuf Goth, Landhi was completed. The project has massively improved pressures for the consumers belonging to all sectors located in Landhi Area.In June 2024, the Company commissioned its 20” dia. x 9 Km pipeline from Azeempura to Jam Sadiq Ali Bridge to subside gas pressure issues in Korangi and adjoining areas.