Consolidating infrastructure – Transmission remains at the forefront

SSGC’s Transmission Department is at the forefront of consolidating the Company’s gas transmission infrastructure. Here is the snapshot of some of the recent (FY 2022-23) tasks carried out by the Department:

  1. Average gas volume handled of around 1665 MMCFD in transmission network.
  2. Lowering of 12” dia. Mehar Pipeline carried out at Mazarani Nala exposed due to heavy flooding.
  3. Up-gradation of SMS Gharhi Khuda Bux carried out to meet gas load requirement.
  4. 12” dia. Rehman Pipeline protection work carried out at KMP-25 and KMP-40 Rain Nala undertaken through casting of CC Structure.
  5. Rehabilitation of HQ-3 domestic gas piping network carried out.
  6. LHF Plant operational integrity reviewed and repairs of re-boilers, Return pump, circulating pump, Stabilizer gate valve, sump pump, MCC panel and Thermal insulation with sheet cladding on re-boiler carried out at HQ-3.
  7. Leak survey with rectification of leakages at 261 MVAs and 12 SMSs on transmission network carried out.
  8. Sleeving job carried on 12” dia. QPL at KMP-342 and on 12” dia. Zarghoun Pipeline in Quetta section carried out.
  9. For RLNG transportation,  Solar T60 engine at Berth B of HQ2 compression station replaced with New engine after completing 30K running hours.
  10. For uninterrupted supply of power, Guascor Gas Generator C 1MW FGLD 560 in house scheduled maintenance carried out after 15K hours at HQ-2