➢ Rehabilitation of Distribution network has been re-strategized. The quantum of network rehabilitation effort has been amped up to over 600 Km per annum.
➢ A master plan is under development, aiming to rehabilitate of around 4,500 Km distribution network in next 3 years.
➢ Network Rehabilitation works in FY 2021-22: Karachi (285Km), Interior Sindh 180 Km, Balochistan (4Km).
– Network Rehabilitation works in FY 2022-23: Karachi (492Km), Interior Sindh (202 Km), Balochistan (49 Km).
➢ Major rehabilitation schemes in the interior Sindh region are planned in 3 cities i.e., Kandhkot: 113 Km, Shahdadkot: 92 Km, Sakrand: 75 Km.
➢ Execution phase started for around 800 KM network rehabilitation schemes in respect of DHA phases I,II, V , VI & VII. Rehabilitation works completed for Phase I and II. Rehabilitation of Phase VI shall be completed in a couple of months, whereas work in Phase V and VII will start soon.
➢ Projects to rehabilitate around 400Km distribution pipelines in Lyari and Baldia have been planned.
➢ F.B. Area, North Nazimabad schemes and Korangi schemes of around 750 Km are in planning phase.
➢ Through these endeavors service delivery will improve in the tail-end areas of the distribution network.
➢ A master plan has already chalked out, aiming to rehabilitate of around 4,500 Km distribution network in next 3 years.
➢ Another project to rehabilitate around 400Km distribution pipelines in Lyari is under final stages of planning. Through these endeavors service delivery will improve in the tail-end areas of the distribution network by laying proper size pipelines, which will substantially reduce customer complaints.